Energy Auction - Phase II
The following is intended to provide interested parties with relevant information concerning the status of developmental efforts associated with the expansion of Southern Companies' Energy Auction to include third party sellers. The information set forth herein is subject to revision by Southern Companies, both for purposes of this posting and for the upcoming filing with the Federal Energy Regulatory Commission.
August 3, 2009 Technical Conference
Revised Participant Agreement
Auction Clearning Methodology
Independent Auction Administrator
- Southern Company is currently in negotiations with a third party (to be identified after contract is signed) to outsource Independent Auction Administrator services.
Proposed Tariff Changes
Expected Implementation Schedule
| Compliance Filing at FERC | 10/19/2009 | |
| Begin User Registration Process | 11/30/2009 | |
| User Acceptance Testing of Software | 12/1/2009-12/15/2009 | |
| Mock Auctions | 12/15/2009-12/16/2009 |
Phase II Start Date/Time
| First Hour Ahead Auction | 1/6/2010 11:45 AM for HE 14 Delivery | |
| First Day Ahead Auction | 1/6/2010 12:00 Noon for 1/6/2010 Delivery |